Finishing the hull, 2012
Looking at the depleted woodpile in May 2012, the remaining planks were checked against the shift of butts plan to provide a final list of what we’ll need to complete the hull.
Read more “Finishing the hull, 2012”Looking at the depleted woodpile in May 2012, the remaining planks were checked against the shift of butts plan to provide a final list of what we’ll need to complete the hull.
Read more “Finishing the hull, 2012” →‘Cachalot’ was honoured to receive one of the National Transport Trust Restoration Awards in 2009, sufficient to purchase the majority of the planking.
Read more “Restart planking and receive an Award, 2010” →With good progress on the frames, by October 2008 it was time to think about ordering wood for the planking.
Read more “Frames, knees, bends and planking, 2008” →New Year 2008 found Paul working on the counter to replace the archboard, deck beams and frames. More new wood to replace the rot certainly began to raise our spirits.
Read more “New wood going in, 2008!” →In August 2007 we were told by Richard, owner of the Tidemill YH, that ‘Cachalot’ would be moved to the far end (aka ‘graveyard’) of the Marina.
Read more “A tent, a workshop and up with the deck!” →By April 2007 it became clear that the problems extended far beyond the counter.
Read more “Assessing the scope of the project, 2007” →